Question Details

[answered] M11 Problem Asmt Scheduling KEY NOTE: 1 There are 2 problem


M11 Problem Asmt

Scheduling

KEY

NOTE:

  • There are 2 problems for this topic
  • Must be in Word Document!

#1)

Jobs A, B, C, D and E must go through Processes I and II in that sequence (Process I first, then Process II).

  • Use Johnson?s rule to determine the optimal sequence in which to schedule the jobs to minimize the total required time. (7 points)
  • If jobs were processed in the sequence: A-B-C-D-E, when will job ?B? be completed? ?(3 points)

JOB

Required Processing Time on Process (Machine) I (in hours)

Required Processing Time on Process (Machine) II (in hours)

A

4

5

B

16

14

C

10

7

D

13

11

E

3

9

?#2)

The following table contains information regarding jobs that are to be scheduled through one machine:

OPERATIONS TIME

JOB

PROCESSING TIME(DAYS)

DUE DATE

A

4

20

B

12

30

C

2

15

D

11

16

E

10

18

F

3

5

G

6

9

  • What is the shortest operating time (SOT) schedule? (2 points)
  • What is the slack time remaining (STR) schedule? (4 points)
  • For the schedule F-G-C-D-E-A-B, compute average lateness? (4 points)

M11 Problem Asmt

 

Scheduling

 

KEY

 

NOTE:

 

1 There are 2 problems for this topic

 

2 Must be in Word Document!

 

#1)

 

Jobs A, B, C, D and E must go through Processes I and II in that sequence (Process I first, then

 

Process II).

 

a) Use Johnson?s rule to determine the optimal sequence in which to schedule the jobs to

 

minimize the total required time. (7 points)

 

b) If jobs were processed in the sequence: A-B-C-D-E, when will job ?B? be completed? (3

 

points) JOB

 

A

 

B

 

C

 

D

 

E Required Processing

 

Time on Process

 

(Machine) I (in hours)

 

4

 

16

 

10

 

13

 

3 Required Processing

 

Time on Process

 

(Machine) II (in hours)

 

5

 

14

 

7

 

11

 

9 #2)

 

The following table contains information regarding jobs that are to be scheduled through one

 

machine: OPERATIONS TIME

 

JO

 

B

 

A

 

B

 

C

 

D

 

E

 

F

 

G PROCESSING TIME(DAYS)

 

4

 

12

 

2

 

11

 

10

 

3

 

6 DUE DATE

 

20

 

30

 

15

 

16

 

18

 

5

 

9 a) What is the shortest operating time (SOT) schedule? (2 points)

 

b) What is the slack time remaining (STR) schedule? (4 points)

 

c) For the schedule F-G-C-D-E-A-B, compute average lateness? (4 points)

 


Solution details:
STATUS
Answered
QUALITY
Approved
ANSWER RATING

This question was answered on: Sep 18, 2020

PRICE: $15

Solution~0001013381.zip (25.37 KB)

Buy this answer for only: $15

This attachment is locked

We have a ready expert answer for this paper which you can use for in-depth understanding, research editing or paraphrasing. You can buy it or order for a fresh, original and plagiarism-free copy from our tutoring website www.aceyourhomework.com (Deadline assured. Flexible pricing. TurnItIn Report provided)

Pay using PayPal (No PayPal account Required) or your credit card . All your purchases are securely protected by .
SiteLock

About this Question

STATUS

Answered

QUALITY

Approved

DATE ANSWERED

Sep 18, 2020

EXPERT

Tutor

ANSWER RATING

GET INSTANT HELP/h4>

We have top-notch tutors who can do your essay/homework for you at a reasonable cost and then you can simply use that essay as a template to build your own arguments.

You can also use these solutions:

  • As a reference for in-depth understanding of the subject.
  • As a source of ideas / reasoning for your own research (if properly referenced)
  • For editing and paraphrasing (check your institution's definition of plagiarism and recommended paraphrase).
This we believe is a better way of understanding a problem and makes use of the efficiency of time of the student.

NEW ASSIGNMENT HELP?

Order New Solution. Quick Turnaround

Click on the button below in order to Order for a New, Original and High-Quality Essay Solutions. New orders are original solutions and precise to your writing instruction requirements. Place a New Order using the button below.

WE GUARANTEE, THAT YOUR PAPER WILL BE WRITTEN FROM SCRATCH AND WITHIN YOUR SET DEADLINE.

Order Now